E&S Plan Review/NPDES Permit Decision Timetable
The following are the maximum review/decision time frames for conservation district decisions related to Erosion & Sediment Control Plan reviews and NPDES permit applications as defined by PA DEP Administrative Policy. These time frames do not include the time it takes for applicants or their consultants to respond to the conservation district’s requests for additional or revised information. They also do not include DEP’s time frames for conducting post-construction stormwater management reviews and related permit decisions for Individual NPDES Permits.
General Permit = 80 days
20 days to conduct administrative review
30 days to conduct 1st technical review
30 days to conduct 2nd technical review/record of decision
Individual Permit = 118 days
20 days to conduct administrative review
66 days to conduct 1st technical review
32 days to conduct 2nd technical review/record of decision